By Stephen Varone, AIA
President, RAND Engineering & Architecture, DPC

A RAND construction sign.

Well-run construction projects have firm start and completion dates for each phase.

1. Schedule a Project Initiation Conference
2. Carefully Review the Project Timeline
3. Have a Full-time Project Superintendent
4. Require Daily Reports
5. Request Written Reports from the Engineer/Architect
6. Hold Periodic Job Meetings
7. Include a Liquidated Damages Clause in the Contract

Contractors hate this one, but no one can deny its effectiveness. Let’s assume the contractor is replacing both your roof and the roof of a neighboring building. Both contracts call for a 12-week completion, but only your contract calls for a liquidated damages assessment of $500 for each day the project extends beyond the deadline. Guess which schedule will be more closely monitored by the contractor? Construction projects mean disruptions. Residents and shareholders may grudgingly accept a 12-week construction imposition but they will not easily–or quietly–accept one that unnecessarily becomes 24.

8. Insist on at Least 10 Percent Retainage

The best defense against being saddled with unfinished punch-list items is to insist that a retainage of at least 10 percent of the contract amount be held back until at least 30 days after the engineer/architect has signed off the completed project. The 30-day period is important because it allows you time to investigate whether any new punch-list items develop. The 10 percent minimum figure is important because it is substantial enough to keep the contractor motivated and can comfortably cover the costs of having punch-list items completed by another firm if the contractor neglects or is unable to finish the work.

While these eight steps are by no means the only essential elements of a well-run construction project, incorporating them will substantially increase the likelihood of successful results.