By Lisa L. Colangelo

Independence House, a seven-story, 51-unit co-op in the Spuyten Duyvil section of the Bronx, was due for a facelift. Kennita Anderson, the property manager from Robert E. Hill, says water had seeped into the concrete in the terraces since the building opened in 1953, causing damage to the reinforcing bars and supporting steel I-beams. Additionally, there was “spalling” on the undersides of some balconies, where the concrete was flaking and chipping, according to Jim Macho, an architect who is president of the co-op board. “We wanted to get that removed to prevent anyone from getting injured,” he says.

Independence House, a 51-unit co-op in the Spuyten Duyvil section of the  the Bronx, where RAND’s opinion saved big money on a balcony project.
Independence House, a 51-unit co-op in the Spuyten Duyvil section of the the Bronx, where RAND’s opinion saved big money on a balcony project.
Heavy Handed Hammers

After the original project engineer died unexpectedly, the board hired a design-build contractor who proved to be “heavy-handed,” according to Anderson. The contractor used a jackhammer to remove the spalling which, experts say, is usually performed with smaller hammers. The jackhammers removed more concrete than necessary from the terraces, in turn exposing rebars to the elements, says Macho. “The contractor who was to repair the terraces came back and said all 36 terraces would need to be completely removed and replaced,” he adds. “It was at that time it was decided to get another opinion. I knew the terraces could be fixed, as opposed to a teardown.”

Sticker Shock

The estimated price tag for demolishing and replacing all the terraces was about $1.2 million, which, Anderson says, sent the board went into “sticker shock” and led to a question: “Why demolish all these balconies when we can fix them?”

“Hire a Professional”

Macho’s advice? “Hire a professional engineer or architect to do drawings and specifications for the project, and get involved in the bidding process. They’re also there during the construction to make sure the owner is getting what he’s paying for. Design-build contractors can steer it to be done a certain way. RAND was on top of the contractor during the work.” Adds Hobson: “When you have a bad feeling about something, hire another engineer. We ended up saving them nearly half—and that’s with engineering oversight fees.”

From Habitat Magazine, April 19, 2017.